Oct. 27, 2025—CMOC Group recently announced that it plans to invest $1.084 billion to construct the Phase II project of the KFM mine in the Democratic Republic of the Congo (DRC). The funding will come from the company’s own funds and self-raised funds.
With a construction period of two years, the project is scheduled to be completed and operational by 2027. It is expected to add an annual raw ore processing capacity of 7.26 million tons and produce an average of 100,000 tons of copper metal per year at full capacity.
According to the announcement, CMOC indirectly holds a 71.25% equity interest in the KFM mine in the DRC. As one of the world’s largest and highest-grade operating copper mines, the Phase I project of the KFM mine reached full production in 2023. To fully leverage its resource potential, the company has initiated the Phase II project, aiming to create synergies with existing operations through capacity expansion.
As planned, the KFM Phase II project is an integrated mining, mineral processing, and metallurgy operation. It will add an annual mining and processing capacity of 7.26 million tons of sulfide ore, expand smelting facilities based on the Phase I hydrometallurgical plant, and retrofit the Phase I processing plant to increase flotation capacity for mixed ore. The project is designed to have a service life of 15 years.